Isolation of pile body concrete

reinforced piles During a certain period of time the mudcake around the concrete filling pile will thicken along with holing time while the ultimate bearing capacity of the pile will decrease along with the thickening

PILE LOAD TEST HPCL

Testing Procedure Pile Loading Test shall be performed in conformity with IS2911 Part IV latest revision The LSTK CONTRACTOR shall design the test beams cross beams through Soil/ Concrete Blocks/Dummy Piles

Vibro Concrete Columns

METHOD STATEMENT FOR VIBRO CONCRETE COL UMN INSTAL LATION Section A Vibro Concrete Column Installation A Introduction Vibro Concrete Columns are cast in place displacement piles installed by a vibroprobe

Concrete Piles

Concrete Piles We offer drilling and pouring of auger cast friction foundation piles using our own auger equipped When installing a pile a critical part in the procedure is the dropping of the cage in the pile